A new long-range assessment of Aberdeen’s water system says the town will need additional reliable supply and substantial infrastructure work to support future growth and maintain flexibility during emergencies.

Demand is approaching available capacity

Aberdeen operates 20 production wells, four elevated storage tanks and approximately 105 miles of water mains. The assessment found that the town’s maximum one-day demand reached 3.759 million gallons, or about 90 percent of total well capacity.

The report says existing wells do not provide adequate capacity for emergency conditions and that approved development will consume remaining capacity. Projected growth could require another 1.7 to 2.5 million gallons per day by 2045, roughly equivalent to eight to 12 additional wells.

A 20-year improvement plan

Engineers recommended evaluating both groundwater and surface-water alternatives, improving connections between pressure zones and establishing routine replacement programs for older water mains and aging well components.

The assessment also found seven wells in good condition, eight in fair condition, three in poor condition and two in very poor condition. Aberdeen’s four elevated tanks, with combined storage of 1.6 million gallons, were rated in good condition.

The plan provides a framework for future budgeting and grant applications; the presentation itself did not approve every proposed project. Sources: The Pilot and the Town of Aberdeen board packet.

Share:

Facebook
Twitter
Pinterest
LinkedIn

Social Media

Most Popular

Stay connected to Sandhills.

Subscribe To Our Weekly Newsletter

We send one helpful email a week with new releases, special moments, and what’s coming up next.

Related Posts

Duke Energy
Sandhills Local News

Duke Energy Residential Rate Increases Begin in January

Many North Carolina households will see higher electric bills beginning Jan. 1 after state regulators approved two-year rate plans for Duke Energy Progress and Duke Energy Carolinas. Projected household impact Residential rates are projected to rise approximately 9.3 percent over two years for Duke Energy Progress customers and 9.5 percent for Duke Energy Carolinas customers. For a typical household using 1,000 kilowatt-hours each month, Duke projects that a Progress customer would pay $9.62 more per

Read More »
Town of Aberdeen
Sandhills Local News

Aberdeen Water Assessment Maps Out Capacity Needs Through 2045

A new long-range assessment of Aberdeen’s water system says the town will need additional reliable supply and substantial infrastructure work to support future growth and maintain flexibility during emergencies. Demand is approaching available capacity Aberdeen operates 20 production wells, four elevated storage tanks and approximately 105 miles of water mains. The assessment found that the town’s maximum one-day demand reached 3.759 million gallons, or about 90 percent of total well capacity. The report says existing

Read More »
Sandhills Local News

Federal Law Advances New Veterans Home Near Fort Bragg

A major land-transfer hurdle has been cleared for a planned state veterans home near Fort Bragg that could serve eligible veterans throughout the Sandhills. Twenty-acre site authorized President Donald Trump signed H.R. 10159 into law Friday, authorizing the U.S. Army to transfer approximately 20 acres in the Fort Bragg Training Area in Harnett County to North Carolina. The property would be used for a state veterans home operated under the North Carolina Department of Military

Read More »