A new long-range assessment of Aberdeen’s water system says the town will need additional reliable supply and substantial infrastructure work to support future growth and maintain flexibility during emergencies.
Demand is approaching available capacity
Aberdeen operates 20 production wells, four elevated storage tanks and approximately 105 miles of water mains. The assessment found that the town’s maximum one-day demand reached 3.759 million gallons, or about 90 percent of total well capacity.
The report says existing wells do not provide adequate capacity for emergency conditions and that approved development will consume remaining capacity. Projected growth could require another 1.7 to 2.5 million gallons per day by 2045, roughly equivalent to eight to 12 additional wells.
A 20-year improvement plan
Engineers recommended evaluating both groundwater and surface-water alternatives, improving connections between pressure zones and establishing routine replacement programs for older water mains and aging well components.
The assessment also found seven wells in good condition, eight in fair condition, three in poor condition and two in very poor condition. Aberdeen’s four elevated tanks, with combined storage of 1.6 million gallons, were rated in good condition.
The plan provides a framework for future budgeting and grant applications; the presentation itself did not approve every proposed project. Sources: The Pilot and the Town of Aberdeen board packet.